The Capability Maturity Model for Software
Mark C. Paulk
Software Engineering Institute
Bill Curtis
Software Engineering Institute
Mary Beth Chrissis
Software Engineering Institute
Charles V. Weber
IBM Federal Systems Company
|
The Capability Maturity Model for Software |
|
|
Abstract |
|
|
Keywords |
|
|
Introduction |
|
|
Immature Versus Mature Software Organizations |
|
|
Fundamental Concepts Underlying Process Maturity |
|
|
The Five Levels of Software Process Maturity |
|
|
Behavioral Characterization of the Maturity Levels |
|
|
Level 1 - The Initial Level |
|
|
Level 2 - The Repeatable Level |
|
|
Level 3 - The Defined Level |
|
|
Level 4 - The Managed Level |
|
|
Level 5 - The Optimizing Level |
|
|
Process Capability and the Prediction of Performance |
|
|
Skipping Maturity Levels |
|
|
Internal Structure of the Maturity Levels |
|
|
Maturity Levels |
|
|
Key Process Areas: Level 1 , Level 2 , Level 3 , Level 4 , Level 5 |
|
|
Goals |
|
|
Common Features |
|
|
Key Practices |
|
|
Future Directions of the CMM |
|
|
Conclusion |
|
|
References |
|
|
For More Information |
|
|
|
|
This paper provides an
overview of the Capability Maturity Model for Software, CMM v1.1. At the time, based on over six years of experience with software
process improvement and the contributions of hundreds of reviewers.
CMM v1.1 describes the software engineering and management practices that
characterize organizations as they mature their processes for developing and
maintaining software. This paper stresses the need for a process maturity
framework to prioritize improvement actions, describes the process maturity
framework of five maturity levels and the associated structural components, and
discusses future directions for the CMM. TOC
Capability
maturity model, CMM, process maturity framework, software process improvement,
process capability, process performance, maturity level, key process area,
software process assessment, software capability evaluation. TOC
After two decades of
unfulfilled promises about productivity and quality gains from applying new
software methodologies and technologies, organizations are realizing that their
fundamental problem is the inability to manage the software process. In many
organizations, projects are often excessively late and over budget, and the
benefits of better methods and tools cannot be realized in the maelstrom of an
undisciplined, chaotic project.
In November 1986, the
Software Engineering Institute (SEI), with assistance from the Mitre Corporation, began developing a process maturity
framework that would help organizations improve their software process. In
September 1987, the SEI released a brief description of the process maturity
framework [Humphrey 87a] which was later expanded in Humphrey's book, Managing
the Software Process [Humphrey89]. Two methods, software process assessment
1 and software capability evaluation 2 and a maturity questionnaire
[Humphrey87b] were developed to appraise software process maturity.
After four years of
experience with the software process maturity framework and the preliminary
version of the maturity questionnaire, the SEI evolved the maturity framework
into the Capability Maturity Model for Software (CMM) [Paulk91, Weber91]. The
CMM presents sets of recommended practices in a number of key process areas
that have been shown to enhance software process capability. The CMM is based
on knowledge acquired from software process assessments and extensive feedback
from both industry and government.
The Capability Maturity
Model for Software provides software organizations with guidance on how to gain
control of their processes for developing and maintaining software and how to
evolve toward a culture of software engineering and management excellence. The
CMM was designed to guide software organizations in selecting process
improvement strategies by determining current process maturity and identifying
the few issues most critical to software quality and process improvement. By
focusing on a limited set of activities and working aggressively to achieve
them, an organization can steadily improve its organization-wide software
process to enable continuous and lasting gains in software process capability.
The
initial release of the CMM, v1.0, was reviewed and used by the software
community during 1991 and 1992. A workshop was held in April, 1992 on CMM v1.0,
and was attended by about 200 software professionals. The current version of
the CMM, v1.1 [Paulk93a, Paulk93b], is the result of the feedback from that
workshop and ongoing feedback from the software community. TOC
1.1 Immature Versus Mature Software Organizations
Setting sensible goals
for process improvement requires an understanding of the difference between
immature and mature software organizations. In an immature software
organization, software processes are generally improvised by practitioners and
their management during the course of the project. Even if a software process
has been specified, it is not rigorously followed or enforced. The immature
software organization is reactionary, and managers are usually focused on
solving immediate crises (better known as fire fighting).
Schedules and budgets are
routinely exceeded because they are not based on realistic estimates. When hard
deadlines are imposed, product functionality and quality are often compromised
to meet the schedule.
In an immature
organization, there is no objective basis for judging product quality or for
solving product or process problems. Therefore, product quality is difficult to
predict. Activities intended to enhance quality such as reviews and testing are
often curtailed or eliminated when projects fall behind schedule.
On the other hand, a
mature software organization possesses an organization-wide ability for
managing software development and maintenance processes. The software process
is accurately communicated to both existing staff and new employees, and work
activities are carried out according to the planned process.
The processes mandated
are usable and consistent with the way the work actually gets done. These
defined processes are updated when necessary, and improvements are developed
through controlled pilot-tests and/or cost benefit analyses. Roles and
responsibilities within the defined process are clear throughout the project
and across the organization.
In a mature organization,
managers monitor the quality of the software products and the process that
produced them. There is an objective, quantitative basis for judging product
quality and analyzing problems with the product and process.
Schedules
and budgets are based on historical performance and are realistic; the expected
results for cost, schedule, functionality, and quality of the product are
usually achieved. In general, a disciplined process is consistently followed
because all of the participants understand the value of doing so, and the
necessary infrastructure exists to support the process. TOC
1.2 Fundamental Concepts Underlying Process Maturity
A software process can
be defined as a set of activities, methods, practices, and transformations that
people use to develop and maintain software and the associated products (e.g.,
project plans, design documents, code, test cases, and user manuals). As an
organization matures, the software process becomes better defined and more
consistently implemented throughout the organization.
Software process
capability describes
the range of expected results that can be achieved by following a software
process. The software process capability of an organization provides one means
of predicting the most likely outcomes to be expected from the next software
project the organization undertakes.
Software process
performance represents
the actual results achieved by following a software process. Thus, software
process performance focuses on the results achieved, while software process
capability focuses on results expected.
Software process
maturity is
the extent to which a specific process is explicitly defined, managed,
measured, controlled, and effective. Maturity implies a potential for growth in
capability and indicates both the richness of an organization's software
process and the consistency with which it is applied in projects throughout the
organization. As a software organization gains in software process maturity, it
institutionalizes its software process via policies, standards, and
organizational structures. Institutionalization entails building an
infrastructure and a corporate culture that supports the methods, practices,
and procedures of the business so that they endure after those who originally
defined them have gone. TOC
2 The Five Levels of Software Process Maturity
Continuous process
improvement is based on many small, evolutionary steps rather than
revolutionary innovations. The staged structure of the CMM is based on
principles of product quality espoused by Walter Shewart,
W. Edwards Deming, Joseph Juran, and Philip Crosby.
The CMM provides a framework for organizing these evolutionary steps into five
maturity levels that lay successive foundations for continuous process
improvement. These five maturity levels define an ordinal scale for measuring
the maturity of an organization's software process and for evaluating its
software process capability. The levels also help an organization prioritize
its improvement efforts.
A maturity level is
a well-defined evolutionary plateau toward achieving a mature software process.
Each maturity level comprises a set of process goals that, when satisfied,
stabilize an important component of the software process. Achieving each level
of the maturity framework establishes a different component in the software
process, resulting in an increase in the process capability of the
organization.
Organizing the CMM into
the five levels shown in Figure 2.1 prioritizes improvement actions for
increasing software process maturity. The labeled arrows in Figure 2.1 indicate
the type of process capability being institutionalized by the organization at
each step of the maturity framework. TOC
2.1 Behavioral Characterization of the Maturity
Levels
Maturity Levels 2 through
5 can be characterized through the activities performed by the organization to
establish or improve the software process, by activities performed on each
project, and by the resulting process capability across projects. A behavioral
characterization of Level 1 is included to establish a base of comparison for
process improvements at higher maturity levels. TOC
2.1.1
Level 1 - The Initial Level
At the Initial Level, the
organization typically does not provide a stable environment for developing and
maintaining software. Such organizations frequently have difficulty making
commitments that the staff can meet with an orderly engineering process,
resulting in a series of crises.
Figure 2.1 The Five Levels of
Software Process Maturity

During a crisis, projects
typically abandon planned procedures and revert to coding and testing. Success
depends entirely on having an exceptional manager and a seasoned and effective
software team. Occasionally, capable and forceful software managers can
withstand the pressures to take shortcuts in the software process; but when they
leave the project, their stabilizing influence leaves with them. Even a strong
engineering process cannot overcome the instability created by the absence of
sound management practices.
In spite of this ad hoc,
even chaotic, process, Level 1 organizations frequently develop products that
work, even though they may be over the budget and schedule. Success in Level 1
organizations depends on the competence and heroics of the people in the
organization and cannot be repeated unless the same competent individuals are
assigned to the next project. Thus, at Level 1, capability is a characteristic
of the individuals, not of the organization. TOC
2.1.2
Level 2 - The Repeatable Level
At the Repeatable Level,
policies for managing a software project and procedures to implement those
policies are established. Planning and managing new projects is based on
experience with similar projects.
Process capability is
enhanced by establishing basic process management discipline on a project by
project basis.
R An effective process can be characterized as one which is practiced, documented, enforced, trained, measured, and able to improve.
R Projects in Level 2 organizations have installed basic software management controls.
R Realistic project commitments are based on the results observed on previous projects and on the requirements of the current project.
R The software managers for a project track software costs, schedules, and functionality; problems in meeting commitments are identified when they arise.
R Software requirements and the work products developed to satisfy them are baselined, and their integrity is controlled.
R Software project standards are defined, and the organization ensures they are faithfully followed. The software project works with its subcontractors, if any, to establish a customer-supplier relationship.
Processes may differ
between projects in a Level 2 organization. The organizational requirement for
achieving Level 2 is that there are policies that guide the projects in
establishing the appropriate management processes.
The software process
capability of Level 2 organizations can be summarized as disciplined because
planning and tracking of the software project is stable and earlier successes
can be repeated. The project's process is under the effective control of a
project management system, following realistic plans based on the performance
of previous projects. TOC
2.1.3
Level 3 - The Defined Level
At the Defined Level, the
standard process for developing and maintaining software across the
organization is documented, including both software engineering and management
processes, and these processes are integrated into a coherent whole. This
standard process is referred to throughout the CMM as the organization's
standard software process.
R Processes established at Level 3 are used (and changed, as appropriate) to help the software managers and technical staff perform more effectively.
R The organization exploits effective software engineering practices when standardizing its software processes.
R There is a group that is responsible for the organization's software process activities, e.g., a software engineering process group, or SEPG [Fowler90].
R An organization-wide training program is implemented to ensure that the staff and managers have the knowledge and skills required to fulfill their assigned roles.
R Projects tailor the organization's standard software process to develop their own defined software process, which accounts for the unique characteristics of the project.
R This tailored process is referred to in the CMM as the project's defined software process.
A defined software process contains a coherent, integrated set of well-defined software engineering and management processes.
R A well-defined process can be characterized as including readiness criteria, inputs, standards and procedures for performing the work, verification mechanisms (such as peer reviews), outputs, and completion criteria. Because the software process is well defined, management has good insight into technical progress on all projects.
The software process
capability of Level 3 organizations can be summarized as standard and
consistent because both software engineering and management activities are
stable and repeatable. Within established product lines, cost, schedule, and
functionality are under control, and software quality is tracked. This process
capability is based on a common, organization-wide understanding of the activities,
roles, and responsibilities in a defined software process. TOC
2.1.4
Level 4 - The Managed Level
At the Managed Level, the
organization sets quantitative quality goals for both software products and
processes.
R Productivity and quality are measured for important software process activities across all projects as part of an organizational measurement program. An organization-wide software process database is used to collect and analyze the data available from the projects' defined software processes.
R Software processes are instrumented with well-defined and consistent measurements at Level 4. These measurements establish the quantitative foundation for evaluating the projects' software processes and products.
R Projects achieve control over their products and processes by narrowing the variation in their process performance to fall within acceptable quantitative boundaries. Meaningful variations in process performance can be distinguished from random variation (noise), particularly within established product lines.
R The risks involved in moving up the learning curve of a new application domain are known and carefully managed.
The software process
capability of Level 4 organizations can be summarized as being quantifiable and
predictable because the process is measured and operates within measurable
limits. This level of process capability allows an organization to predict
trends in process and product quality within the quantitative bounds of these
limits.
Because the process is
both stable and measured, when some exceptional circumstance occurs, the
"special cause" of the variation can be identified and addressed.
When the known limits of the process are exceeded, action is taken to correct
the situation. Software products are of predictably high quality. TOC
2.1.5
Level 5 - The Optimizing Level
At the Optimizing Level,
the entire organization is focused on continuous process improvement. The
organization has the means to identify weaknesses and strengthen the process
proactively, with the goal of preventing the occurrence of defects.
R Data on the effectiveness of the software process is used to perform cost benefit analyses of new technologies and proposed changes to the organization's software process. Innovations that exploit the best software engineering practices are identified and transferred throughout the organization.
R Software project teams in Level 5 organizations analyze defects to determine their causes. Software processes are evaluated to prevent known types of defects from recurring, and lessons learned are disseminated to other projects.
R There is chronic waste, in the form of rework, in any system simply due to random variation. Waste is unacceptable; organized efforts to remove waste result in changing the system, i.e., improving the process by changing "common causes" of inefficiency to prevent the waste from occurring. While this is true of all the maturity levels, it is the focus of Level 5.
The software process
capability of Level 5 organizations can be characterized as continuously
improving because Level 5 organizations are continuously striving to improve
the range of their process capability, thereby improving the process
performance of their projects. Improvement occurs both by incremental
advancements in the existing process and by innovations using new technologies
and methods. Technology and process improvements are planned and managed as
ordinary business activities.
TOC
2.2 Process Capability
and the Prediction of Performance
The maturity of an
organization's software process helps to predict a project's ability to meet
its goals. Projects in Level 1 organizations experience wide variations in
achieving cost, schedule, functionality, and quality targets.
As illustrated in Figure
2.4, three improvements in meeting targeted goals are expected as the
organization's software process matures. These expectations are based on the
quantitative results process improvement has achieved in other industries, and
they are consistent with the initial case study results reported from software
organizations [Dion92, Humphrey91b, Lipke92,
Wohlwend93].
First, as maturity
increases, the difference between targeted results and actual results decreases
across projects. For instance, Level 1 organizations often miss their
originally scheduled delivery dates by a wide margin, whereas higher maturity
level organizations should be able to meet targeted dates with increased
accuracy. (This is illustrated in Figure 2.4 by how much of the area under the
curve lies to the right of the target line.)
Second,
as maturity increases, the variability of actual results around targeted
results decreases.
For instance, in Level 1 organizations delivery dates for projects of similar
size are unpredictable and vary widely. Similar projects in a higher maturity
level organization, however, will be delivered within a smaller range. (This is
illustrated in Figure 2.4 by how much of the area under the curve is concentrated
near the target line.)
Third, targeted results
improve as the maturity of the organization increases. That is, as a software
organization matures, costs decrease, development time becomes shorter, and
productivity and quality increase. In a Level 1 organization, development time
can be quite long because of the amount of rework that must be performed to
correct mistakes.
In contrast, higher
maturity level organizations have increased process efficiency and reduce
costly rework, allowing development time to be shortened. (This is illustrated
in Figure 2.4 by the horizontal displacement of the target line from the
origin.) The improvements in predicting a project's results represented in
Figure 2.4 assume that the software project's outcomes become more predictable
as noise, often in the form of rework, is removed from the software process.
Unprecedented systems
complicate the picture since new technologies and applications lower the
process capability by increasing variability. Even in the case of unprecedented
systems, the management and engineering practices characteristic of more mature
organizations help identify and address problems earlier in the development
cycle than they would have been detected in less mature organizations. In some
cases a mature process means that "failed" projects are identified
early in the software life cycle and investment in a lost cause is minimized.
The documented case
studies of software process improvement indicate that there are significant
improvements in both quality and productivity as a result of the improvement
effort [Dion92, Humphrey91b, Lipke92, Wohlwend93]. The
return on investment seems to typically be in the 5:1 to 8:1 range for
successful process improvement efforts. TOC
Trying to skip levels is
counterproductive because each maturity level in the CMM forms a necessary
foundation from which to achieve the next level. The CMM identifies the levels
through which an organization should evolve to establish a culture of software
engineering excellence.
Organizations can
institute specific process improvements at any time they choose, even before
they are prepared to advance to the level at which the specific practice is
recommended. However, organizations should understand that the stability of
these improvements is at greater risk since the foundation for their successful
institutionalization has not been completed.
Processes without the
proper foundation fail at the very point they are needed most – under stress –
and they provide no basis for future improvement. For instance, a well-defined
software process that is characteristic of a Level 3 organization,
can be placed at great risk if management makes a poorly planned schedule
commitment or fails to control changes to the baselined
requirements. Similarly, many organizations have collected the detailed data
characteristic of Level 4, only to find that the data were uninterpretable
because of inconsistency in the software development processes.
At the same time, it must
be recognized that process improvement efforts should focus on the needs of the
organization in the context of its business environment, and higher-level
practices may address the current needs of an organization or project. For example,
when prescribing what steps an organization should take to move from Level 1 to
Level 2, frequently one of the recommendations is to establish a software
engineering process group (SEPG), which is an attribute of Level 3
organizations. While an SEPG is not a necessary characteristic of a Level 2
organization, they can be a useful part of the prescription for achieving Level
2. TOC
3 Operational
Definition of the Capability Maturity Model
The CMM is a framework
representing a path of improvements recommended for software organizations that
want to increase their software process capability. This operational
elaboration of the CMM is designed to support the many ways it will be used.
There are at least
four uses of the CMM that are supported:
Because of the diverse
uses of the CMM, it must be decomposed in sufficient detail that actual process
recommendations can be derived from the structure of the maturity levels. This
decomposition also indicates the key processes and their structure that
characterize software process maturity and software process capability. TOC
3.1 Internal Structure of the Maturity Levels
Each maturity level has
been decomposed into constituent parts. With the exception of Level 1, the
decomposition of each maturity level ranges from abstract summaries of each
level down to their operational definition in the key practices, as shown in
Figure 3.1. Each maturity level is composed of several key process areas. Each
key process area is organized into five sections called common features. The
common features specify the key practices that, when collectively addressed,
accomplish the goals of the key process area. TOC
A maturity level is a
well-defined evolutionary plateau toward achieving a mature software process.
Each maturity level indicates a level of process capability, as illustrated
below. For instance, at Level 2 the process capability of an organization has
been elevated from ad hoc to disciplined by
establishing sound project management controls.

Except for Level 1, each
maturity level is decomposed into several key process areas that indicate where
an organization should focus on to improve its software process. Key process
areas identify the issues that must be addressed to achieve a maturity level.
Each key process area identifies a cluster of related activities
that, when performed collectively, achieve a set of goals considered important
for enhancing process capability.
The key process areas have
been defined to reside at a single maturity level.
The path to achieving the
goals of a key process area may differ across projects based on differences in
application domains or environments. Nevertheless, all the goals of a key
process area must be achieved for the organization to satisfy that key process
area.
The adjective
"key" implies that there are process areas (and processes) that are
not key to achieving a maturity level. The CMM does
not describe all the process areas in detail that are involved with developing
and maintaining software.
Certain process areas
have been identified as key determiners of process capability; these are the
ones described in the CMM. The key process areas may be considered the
requirements for achieving a maturity level. To achieve a maturity level, the
key process areas for that level must be satisfied.
The specific practices to
be executed in each key process area will evolve as the organization achieves
higher levels of process maturity. For instance, many of the project estimating
capabilities described in the Software Project Planning key process area at
Level 2 must evolve to handle the additional project data available at Level 3,
as is described in Integrated Software Management. TOC
The key process areas at
Level 2 focus on the software project's concerns related to establishing basic
project management controls. The purpose of Requirements Management is to
establish a common understanding between the customer and the software project
of the customer's requirements that will be addressed by the software project.
This agreement with the customer is the basis for planning and managing the
software project.
The purpose of Software
Project Planning is to establish reasonable plans for performing the software
engineering and for managing the software project. These plans are the
necessary foundation for managing the software project.
The purpose of Software
Project Tracking and Oversight is to establish adequate visibility into actual
progress so that management can take effective actions when the software
project's performance deviates significantly from the software plans.
The purpose of Software
Subcontract Management is to select qualified software subcontractors and
manage them effectively.
The purpose of Software
Quality Assurance is to provide management with appropriate visibility into the
process being used by the software project and of the products being built.
The purpose of Software
Configuration Management is to establish and maintain the integrity of the
products of the software project throughout the project's software life cycle. TOC
The key process areas at
Level 3 address both project and organizational issues, as the organization establishes
an infrastructure that institutionalizes effective software engineering and
management processes across all projects.
The purpose of
Organization Process Focus is to establish the organizational responsibility
for software process activities that improve the organization's overall
software process capability.
The purpose of
Organization Process Definition is to develop and maintain a usable set of
software process assets that improve process performance across the projects
and provide a basis for defining meaningful data for quantitative process
management. These assets provide a stable foundation that can be
institutionalized via mechanisms such as training.
The purpose of Training
Program is to develop the skills and knowledge of individuals so they can
perform their roles effectively and efficiently. Training is an organizational
responsibility, but the software projects should identify their needed skills
and provide the necessary training when the project's needs are unique.
The purpose of Integrated
Software Management is to integrate the software engineering and management
activities into a coherent, defined software process that is tailored from the
organization's standard software process and related process assets. This
tailoring is based on the business environment and technical needs of the
project.
The purpose of Software
Product Engineering is to consistently perform a well-defined engineering
process that integrates all the software engineering activities to produce
correct, consistent software products effectively and efficiently. Software
Product Engineering describes the technical activities of the project, e.g.,
requirements analysis, design, code, and test.
The purpose of Intergroup Coordination is to establish a means for the
software engineering group to participate actively with the other engineering
groups so the project is better able to satisfy the customer's needs
effectively and efficiently.
The purpose of Peer
Reviews is to remove defects from the software work products early and
efficiently. An important corollary effect is to develop a better understanding
of the software work products and of the defects that can be prevented. The
peer review is an important and effective engineering method that can be
implemented via inspections, structured walkthroughs, or a number of other
collegial review methods. TOC
The key process areas at
Level 4 focus on establishing a quantitative understanding of both the software
process and the software work products being built.
The purpose of
Quantitative Process Management is to control the process performance of the
software project quantitatively. Software process performance represents the
actual results achieved from following a software process. The focus is on
identifying special causes of variation within a measurably stable process and
correcting, as appropriate, the circumstances that drove the transient
variation to occur.
The purpose of Software
Quality Management is to develop a quantitative understanding of the quality of
the project's software products and achieve specific quality goals. TOC
The key process areas at
Level 5 cover the issues that both the organization and the projects must address
to implement continuous and measurable software process improvement.
The purpose of Defect
Prevention is to identify the causes of defects and prevent them from
recurring. The software project analyzes defects, identifies their causes, and
changes its defined software process.
The purpose of Technology
Change Management is to identify beneficial new technologies (i.e., tools,
methods, and processes) and transfer them into the organization in an orderly
manner. The focus of Technology Change Management is on performing innovation
efficiently in an ever-changing world.
The purpose of Process
Change Management is to continually improve the software processes used in the
organization with the intent of improving software quality, increasing
productivity, and decreasing the cycle time for product development. TOC
The goals summarize
the key practices of a key process area and can be used to determine whether an
organization or project has effectively implemented the key process area. The
goals signify the scope, boundaries, and intent of each key process area.
Satisfaction of a KPA is determined by achievement of the goals. TOC
For convenience, the
practices that describe the key process areas are organized by common features.
The common features are attributes that indicate whether the implementation and
institutionalization of a key process area is effective, repeatable, and
lasting. The five common features are:
Commitment to
Perform Commitment to Perform describes
the actions the organization must take to ensure that the process is
established and will endure. Commitment to Perform typically involves
establishing organizational policies and senior management sponsorship.
Ability to Perform Ability to Perform describes the
preconditions that must exist in the project or organization to implement the
software process competently. Ability to Perform typically involves resources,
organizational structures, and training.
Activities
Performed Activities Performed describes the
roles and procedures necessary to implement a key process area. Activities
Performed typically involve establishing plans and procedures, performing the
work, tracking it, and taking corrective actions as necessary.
Measurement and
Analysis Measurement and Analysis describes
the need to measure the process and analyze the measurements. Measurement and
Analysis typically includes examples of the measurements that could be taken to
determine the status and effectiveness of the Activities Performed.
Verifying
Implementation
Verifying
Implementation describes the steps to ensure that
the activities are performed in
compliance with the process that has been established. Verification typically
encompasses reviews and audits by management and software quality assurance.
The practices in the
common feature Activities Performed describe what must be implemented to
establish a process capability. The other practices, taken as a whole, form the
basis by which an organization can institutionalize the practices described in
the Activities Performed common feature. TOC
Each key process area is
described in terms of the key practices that contribute to satisfying its
goals.
The key practices describe
the infrastructure and activities that contribute most to the effective
implementation and institutionalization of the key process area.
Each key practice
consists of a single sentence, often followed by a more detailed description,
which may include examples and elaboration. These key practices, also referred
to as the top-level key practices, state the fundamental policies, procedures,
and activities for the key process area.
The components of the
detailed description are frequently referred to as sub practices. The key
practices describe "what" is to be done, but they should not be
interpreted as mandating "how" the goals should be achieved.
Alternative practices may
accomplish the goals of the key process area. The key practices should be
interpreted rationally to judge whether the goals of the key process area are
effectively, although perhaps differently, achieved. The key practices are
contained in the "Key Practices of the Capability Maturity Model, Version
1.1" [Paulk93b], along with guidance on their interpretation. TOC
4
Future Directions of the CMM
Achieving higher levels
of software process maturity is incremental and requires a long-term commitment
to continuous process improvement. Software organizations may take ten years or
more to build the foundation for, and a culture oriented toward, continuous
process improvement. Although a decade-long process improvement program is
foreign to most
The CMM is not a silver
bullet and does not address all of the issues that are important for successful
projects.
For example, the CMM does
not currently address expertise in particular application domains, advocate
specific software technologies, or suggest how to select, hire, motivate, and
retain competent people.
Although these issues are
crucial to a project's success, they have not been integrated into the CMM.
During the next few years, the CMM will continue to undergo extensive testing
through use in software process assessments, software capability evaluations,
and process improvement programs.
CMM-based products and
training materials will be developed and revised as appropriate. The CMM is a
living document that will be improved, but it is anticipated that CMM v1.1 will
remain the baseline until at least 1996. This provides an appropriate and
realistic balance between the needs for stability and for continued
improvement.
A book on the CMM is in
progress for the SEI series published by Addison-Wesley. The SEI is also
working with the International Standards Organization (ISO) in its efforts to
build international standards for software process assessment, improvement, and
capability evaluation.
This effort will integrate
concepts from many different process improvement methods. The development of
the ISO standards (and the contributions of other methods) will influence CMM
v2.0, even as the SEI's process work will influence
the activities of the ISO. TOC
5 Conclusion
The CMM represents a
"common sense engineering" approach to software process improvement.
The maturity levels, key process areas, common features, and key practices have
been extensively discussed and reviewed within the software community. While
the CMM is not perfect, it does
represent a broad consensus of the software
community and is a useful tool for guiding software process improvement
efforts.
The CMM provides a
conceptual structure for improving the management and development of software
products in a disciplined and consistent way. It does not guarantee that
software products will be successfully built or that all problems in software
engineering will be adequately resolved. However, current reports from
CMM-based improvement programs indicate that it can improve the likelihood with
which a software organization can achieve its cost, quality, and productivity
goals. [Dion92, Humphrey91b, Lipke92, Wohlwend93]
The CMM identifies
practices for a mature software process and provides examples of the state
of-the-practice (and in some cases, the state-of-the-art), but it is not meant
to be either exhaustive or dictatorial. The CMM identifies the characteristics
of an effective software process, but the mature organization addresses all
issues essential to a successful project, including people and technology, as
well as process. TOC
Dion92 Raymond Dion, "Elements of a Process-Improvement
Program," IEEE Software, Vol. 9, No. 4, July 1992, pp. 83-85.
Fowler90 P. Fowler and S.
Rifkin, Software Engineering Process Group Guide, Software Engineering
Institute, CMU/SEI-90-TR-24, ADA235784, September, 1990.
Humphrey87a W.S.
Humphrey, Characterizing the Software Process: A Maturity Framework,
Software Engineering Institute, CMU/SEI-87-TR-11, ADA182895, June 1987. Also published in IEEE Software, Vol. 5, No. 2, March 1988,
pp.73-79.
Humphrey87b W.S. Humphrey
and W.L. Sweet, A Method for Assessing the Software Engineering Capability
of Contractors, Software Engineering Institute, CMU/SEI-87-TR-23,
ADA187320, September 1987.
Humphrey89
W.S. Humphrey, Managing the Software Process, Addison-Wesley,
Humphrey91a W.S.
Humphrey, D.H. Kitson, and J. Gale, "A
Comparison of U.S. and Japanese Software Process Maturity," Proceedings
of the 13th International Conference on Software Engineering, Austin, TX,
13-17 May 1991, pp. 38-49.
Humphrey91b
Lipke92 W.H. Lipke and K.L. Butler, "Software Process Improvement:
A Success Story," Crosstalk: The Journal of Defense Software Engineering,
No. 38, November 1992, pp. 29-31.
Paulk91 M.C. Paulk, B. Curtis, M.B. Chrissis,
et al, Capability Maturity Model for Software, Software Engineering
Institute, CMU/SEI-91-TR-24, ADA240603, August 1991.
Paulk93a M.C. Paulk, B. Curtis, M.B. Chrissis,
and C.V. Weber, Capability Maturity Model for Software, Version 1.1,
Software Engineering Institute, CMU/SEI-93-TR-24, February 1993.
Paulk93b M.C. Paulk, C.V. Weber, S. Garcia, M.B. Chrissis,
and M.Bush, Key Practices of the Capability
Maturity Model, Version 1.1, Software Engineering Institute, CMU/SEI-93-
TR-25, February 1993.
Weber91 C.V. Weber, M.C. Paulk, C.J. Wise, and J.V. Withey,
Key Practices of the Capability Maturity Model, Software Engineering
Institute, CMU/SEI-91-TR-25, ADA240604, August 1991.
Wohlwend93 H. Wohlwend and
The Capability Maturity
Model for Software was produced by a dedicated group of people who spent many
hours discussing the model and its features and then trying to document it in
the two versions of the CMM. Contributors to the CMM, other than the authors,
include Edward Averill, Judy Bamberger, Joe Besselman,
Marilyn Bush, Anita Carleton, Marty Carlson, Susan Dart, Betty Deimel, Lionel Deimel, Peter Feiler, Julia Gale, Suzie Garcia, Jim Hart, Ron Higuera, Watts Humphrey, Purvis Jackson, Tim Kasse, Richard Kauffold, David Kitson, Mike Konrad, Peter Malpass, Mark Manduke, Steve
Masters, Mary Merrill, Judah Mogilensky, Warren
Moseley, Jim Over, George Pandelios, Bob Park, Jeff
Perdue, Dick Phillips, Mike Rissman, Jim Rozum, Jane Siegel, Christer von Schantz, Cynthia Wise, and Jim Withey.
We appreciate the
administrative help from Todd Bowman, Dorothy Josephson,
Debbie Punjack, Carolyn Tady,
Marcia Theoret, Andy Tsounos,
and David White; and the editorial assistance from Suzanne Couturiaux
and Bill Pollak.
Special thanks go to the
members of the CMM Correspondence Group, who contributed their time and effort
to reviewing drafts of the CMM and providing insightful comments and recommendations,
and to the members of the CMM Advisory Board, who helped guide us in our
efforts. The current members of the Advisory Board are Constance Ahara, Kelley Butler, Bill Curtis, Conrad Czaplicki, Raymond Dion, Judah Mogilensky, Martin Owens, Mark Paulk,
Sue Stetak, Charlie Weber, and Ron Willis. Former
members who worked with us on CMM v1.0 include Harry Carl, Jim Hess, Jerry Pixton, and Jim Withey. This work
was sponsored by the U.S. Department of Defense. TOC
For further information
regarding the CMM and its associated products, including training on the CMM
and how to perform software process assessments and software capability
evaluations, contact: